Regulatory Perspective: IEEE Std 1547 Revision and Distributed Energy Resource Interconnection Standards

This page provides highlights of the presentation, Regulatory Perspective: Institute of Electrical and Electronics Engineers Standard 1547 (IEEE Std 1547) Revision and Distributed Energy Resource Interconnection Standards.

Presentation

Regulatory Perspective: IEEE Std 1547 Revision and Distributed Energy Resource Interconnection Standards (Rosier 2018)
The presentation was given by Michele Rosier, distributed energy resource specialist at the Minnesota Public Utilities Commission (PUC), at a joint meeting sponsored by the Committee on Regional Electric Power Cooperation and the Western Interconnection Regional Advisory Board on April 20, 2018.

Intended Audiences

  • State regulators
  • Policy makers
  • Energy offices

Topics Discussed

The presentation highlights key considerations and advice for public utility commissions. There are 13 content slides with information based on insights gained from implementation of the Minnesota PUC Order to revise the interconnection process. The presentation includes information on the Minnesotat PUC order, its background, high-level goals for Minnesota, interconnection technical workshops, an overview of the phases and process for the Minnesota update, workgroups and timelines, and bulleted key learnings to date. 

Topics Details
Best practices 

Slide 3: High-level recommendations

Slide 8: Preliminary lessons from Phase II of Minnesota interconnection process update

Slide 9: Familiarization with IEEE Std 1547

Slide 11: Recommendations for working with regional transmission operators, indepement system operators, the National Electric Reliability Council, and neighboring states

Slide 13: Recommendations for working with technical experts

Context of interconnection process Slide 4: Infographic showing interconnection process within broader context of grid modernization
Case study

Slide 5: Highlights from Minnesota PUC order on interconnection process

Slide 6: Breakdown of tasks and timing into phases in Minnesota interconnection update process

Slide 7: Minnesota interconnection workgroup discussion topics and meeting calendar schedule

Slide 10: Summary of Minnesota technical subgroup, with list of individuals

Slide 14: Example interim implementation timeline

Application of the standard and integrating into practice Slide 12: Examples of challenges during discussion, including capabilities versus utilization and reconciling in state requirements
Resources Slide 15: List of resources on interconnection-related material

Share