Viryd Technologies' CS8 Turbine Testing and Results
Viryd Technologies CS8 wind turbine. Text Version
As part of the National Renewable Energy Laboratory and U.S. Department of Energy (NREL/DOE) Independent Testing project, NREL is testing Viryd Technologies' CS8 small wind turbine at the National Wind Technology Center (NWTC). The CS8 is an upwind, horizontal-axis, three-bladed, stall controlled turbine rated at 8 kilowatts (kW). It has an 8.5-meter rotor diameter and is mounted on a guyed tilt-up lattice tower with a hub height of 24.9 meters. The CS8 uses a single-phase, grid-connected, induction generator that operates at 240 volts AC.
Testing Summary
Supporting data and explanations for data provided in this table will be provided in the final reports once testing is complete. Data presented are preliminary and subject to revision.
Cumulative Energy Production
| Activity | Status |
|---|---|
| Award of Grant | December 1, 2009 |
| Preparation for Installation | Foundation installed: August 17, 2010 Components received: September 7, 2011 Documentation received: August 26, 2011 |
| Turbine Installation | September 22, 2011 |
| Turbine Commissioning | Viryd commissioning: October 6, 2011 Readiness verification: November 22, 2011 Data Acquisition System check: October 12, 2011 |
| Turbine O&M and Testing | |
| Safety and Function Test | In progress |
| Power Performance Test | Data collection complete; Report in progress |
Hrs of valid data (60 required) |
740 |
Bins completed (3.5-14 m/s required) |
0.5-19 |
| Acoustic Noise Test | In progress |
| Power Quality Test | Not Applicable |
| Duration Test | In progress |
Months of operation (6 required) |
12; Testing ongoing |
Hours of power production (2,500 required) |
1,629.1; Testing ongoing |
Hours of power production in winds greater than 10.2 m/s (250 required) |
371.4; Testing ongoing |
Hours of power production in winds greater than 15.3 m/s (25 required) |
72; Testing ongoing |
kWh of production, cumulative |
1,795 |
| Turbine Removed | Not applicable |
| Post-test Inspection | Not started |
| Final Documentation | Not started |
| Project Review Meeting | Not started |