Ventera's VT 10 Turbine Testing and Results
As part of the National Renewable Energy Laboratory and U.S. Department of Energy (NREL/DOE) Independent Testing project, NREL is testing Ventera's VT10 small wind turbine at the National Wind Technology Center (NWTC). The VT10 is a horizontal-axis downwind, three-bladed turbine rated at 10 kilowatts (kW). Its diameter is 6.7 meters, and it is mounted on a lattice tower with a hub height of 21.7 meters. The VT10 uses a single-phase, grid-connected, permanent-magnet generator that operates at 240 volts AC.
Testing Summary
The summary of the tests is listed below, along with the final reports.
Cumulative Energy Production
3/29/2010: 26; 3/31/2010: 74; 4/1/2010: 75; 4/2/2010: 174; 4/3/2010: 257; 4/5/2010: 260; 4/6/2010: 311; 4/12/2010: 311; 4/13/2010: 375; 4/14/2010: 431; 4/15/2010: 444; 4/21/2010: 448; 4/22/2010: 455; 4/30/2010: 595; 5/1/2010: 617; 5/4/2010: 758; 5/5/2010: 880; 5/6/2010: 895; 5/12/2010: 963; 5/19/2010: 970; 6/7/2010: 1289; 6/8/2010: 1300; 7/14/2010: 1300; 7/15/2010: 1304; 7/19/2010: 1304; 7/20/2010: 1313; 7/21/2010: 1333; 7/22/2010: 1334; 7/26/2010: 1361; 7/27/2010: 1366; 7/28/2010: 1379; 7/29/2010: 1385; 7/30/2010: 1393; 8/2/2010: 1413; 8/3/2010: 1439; 8/4/2010: 1462; 8/5/2010: 1475; 8/6/2010: 1475; 8/9/2010: 1496; 8/10/2010: 1514; 8/13/2010: 1574; 8/15/2010: 1583; 8/17/2010: 1589; 8/18/2010: 1591; 8/19/2010: 1608; 8/20/2010: 1650; 8/24/2010: 1681; 8/26/2010: 1687; 8/27/2010: 1696; 8/30/2010: 1744; 9/1/2010: 1755; 9/3/2010: 1776; 9/8/2010: 1884; 9/14/2010: 1970; 9/17/2010: 1981; 9/20/2010: 1997; 9/24/2010: 2089; 9/26/2010: 2092; 9/28/2010: 2105; 10/1/2010: 2122; 10/4/2010: 2126; 10/6/2010: 2154; 10/8/2010: 2185; 10/10/2010: 2231; 10/15/2010: 2235; 10/18/2010: 2250; 10/20/2010: 2257; 10/26/2010: 2599; 10/27/2010: 2706; 10/29/2010: 2750; 11/1/2010: 2838; 11/5/2010: 2841; 11/8/2010: 2877; 11/10/2010: 2895; 11/12/2010: 2912; 11/15/2010: 2928; 11/19/2010: 3032; 11/22/2010: 3100; 11/23/2010: 3118; 11/29/2010: 3364; 12/1/2010: 3522; 12/2/2010: 3535; 12/3/2010: 3588; 12/6/2010: 3659; 12/7/2010: 3671; 12/8/2010: 3684; 12/10/2010: 3764; 12/13/2010: 3948; 12/15/2010: 3987; 12/21/2010: 4033; 12/22/2010: 4033; 1/3/2011: 4390; 1/4/2011: 4396; 1/5/2011: 4536; 1/6/2011: 4694; 1/7/2011: 4780; 1/11/2011: 4807; 1/13/2011: 4884; 1/14/2011: 4925; 1/19/2011: 5231; 1/20/2011: 5258; 1/21/2011: 5414; 1/24/2011: 5595; 1/27/2011: 5644; 2/4/2011: 5728; 2/7/2011: 5799; 2/11/2011: 5942; 2/14/2011: 6195; 2/17/2011: 6340; 2/20/2011: 6436; 2/21/2011: 6486; 2/23/2011: 6506; 2/24/2011: 6521; 3/1/2011: 6650; 3/3/2011: 6714; 3/4/2011: 6743; 3/8/2011: 6772; 3/9/2011: 6869; 3/11/2011: 7011; 3/16/2011: 7135; 3/18/2011: 7204; 3/21/2011: 7237; 3/22/2011: 7242; 3/24/2011: 7242; 3/25/2011: 7296; 3/27/2011: 7352; 3/28/2011: 7381; 3/29/2011: 7436; 3/31/2011: 7597; 4/1/2011: 7657; 4/3/2011: 7795; 4/4/2011: 7836; 4/5/2011: 7939; 4/7/2011: 7944; 4/8/2011: 7944; 4/10/2011: 8036; 4/11/2011: 8120; 4/13/2011: 8123; 4/15/2011: 8223; 4/17/2011: 8341; 4/18/2011: 8356; 4/19/2011: 8372; 4/20/2011: 8397; 4/22/2011: 8521; 4/24/2011: 8562; 4/25/2011: 8563; 4/26/2011: 8578; 4/27/2011: 8630; 4/28/2011: 8702; 4/29/2011: 8726; 5/1/2011: 8842; 5/2/2011: 8845; 5/3/2011: 8865; 5/4/2011: 8871; 5/5/2011: 8881; 5/8/2011: 8938; 5/9/2011: 8962; 5/10/2011: 9004; 5/11/2011: 9041; 5/12/2011: 9050; 5/16/2011: 9051; 5/18/2011: 9056; 5/20/2011: 9071; 5/23/2011: 9188; 5/25/2011: 9212; 5/27/2011: 9225; 5/31/2011: 9355; 6/6/2011: 9377; 6/8/2011: 9432; 6/14/2011: 9454;
Activity
Status
Award of Subcontract
Preparation for Installation
Component delivery: June 2009 to March 23, 2010
Foundation installed: December 18, 2009
Documentation delivery: December 2009 to January 29, 2010
Turbine Installation
January 26, 2010
Turbine Commissioning
Ventera Commissioning: January 28, 2010
Inverter Commissioning: March 23, 2010
Turbine O&M and Testing
Safety and Function Test
Wind Turbine Generator System Safety and Function Test Report for the Ventera VT10 Wind Turbine
Power Performance Test
Under Peer Review (restarted on July 27, 2010)
Hrs of valid data (60 required)
548
Bins completed (3.5-14 m/s required)
0.5-25.0 m/s
Acoustic Noise Test
Data Under Analysis
Power Quality Test
Not Applicable
Duration Test
Report Complete; Under Peer Review (or Pending Publication)
Months of operation (6 required)
9.5 (158%)
Hours of power production (2,500 required)
3,206.4 (128%)
Hours of power production in winds greater than 10.2 m/s (250 required)
808.8 (323%)
Hours of power production in winds greater than 15.3 m/s (25 required)
262.4 (1,049%)
kWh of production, cumulative
8,726
Turbine Removed
Complete
Post-test Inspection
Complete
Final Documentation
Complete
Project Review Meeting
Not Applicable