Ventera
As part of the National Renewable Energy Laboratory and U.S. Department of Energy (NREL/DOE) Independent Testing project, NREL is testing Ventera's VT10 small wind turbine at the National Wind Technology Center (NWTC). The VT10 is a downwind, horizontal-axis, three-blade turbine. Its diameter is 6.7 meters, and it is mounted to a lattice tower with a hub height of 21.7 meters. The VT10 uses a single-phase, grid-connected, permanent-magnet generator that is rated at 10 kW at 240 volts AC.
Testing Progress
The date of the information in this progress report is May 1, 2011. Supporting data and explanations for data provided in this table will be provided in the final reports once testing is complete. Data presented are preliminary and subject to revision.
Cumulative Energy Production
3/29/2010: 26; 3/31/2010: 74; 4/1/2010: 75; 4/2/2010: 174; 4/3/2010: 257; 4/5/2010: 260; 4/6/2010: 311; 4/12/2010: 311; 4/13/2010: 375; 4/14/2010: 431; 4/15/2010: 444; 4/21/2010: 448; 4/22/2010: 455; 4/30/2010: 595; 5/1/2010: 617; 5/4/2010: 758; 5/5/2010: 880; 5/6/2010: 895; 5/12/2010: 963; 5/19/2010: 970; 6/7/2010: 1289; 6/8/2010: 1300; 7/14/2010: 1300; 7/15/2010: 1304; 7/19/2010: 1304; 7/20/2010: 1313; 7/21/2010: 1333; 7/22/2010: 1334; 7/26/2010: 1361; 7/27/2010: 1366; 7/28/2010: 1379; 7/29/2010: 1385; 7/30/2010: 1393; 8/2/2010: 1413; 8/3/2010: 1439; 8/4/2010: 1462; 8/5/2010: 1475; 8/6/2010: 1475; 8/9/2010: 1496; 8/10/2010: 1514; 8/13/2010: 1574; 8/15/2010: 1583; 8/17/2010: 1589; 8/18/2010: 1591; 8/19/2010: 1608; 8/20/2010: 1650; 8/24/2010: 1681; 8/26/2010: 1687; 8/27/2010: 1696; 8/30/2010: 1744; 9/1/2010: 1755; 9/3/2010: 1776; 9/8/2010: 1884; 9/14/2010: 1970; 9/17/2010: 1981; 9/20/2010: 1997; 9/24/2010: 2089; 9/26/2010: 2092; 9/28/2010: 2105; 10/1/2010: 2122; 10/4/2010: 2126; 10/6/2010: 2154; 10/8/2010: 2185; 10/10/2010: 2231; 10/15/2010: 2235; 10/18/2010: 2250; 10/20/2010: 2257; 10/26/2010: 2599; 10/27/2010: 2706; 10/29/2010: 2750; 11/1/2010: 2838; 11/5/2010: 2841; 11/8/2010: 2877; 11/10/2010: 2895; 11/12/2010: 2912; 11/15/2010: 2928; 11/19/2010: 3032; 11/22/2010: 3100; 11/23/2010: 3118; 11/29/2010: 3364; 12/1/2010: 3522; 12/2/2010: 3535; 12/3/2010: 3588; 12/6/2010: 3659; 12/7/2010: 3671; 12/8/2010: 3684; 12/10/2010: 3764; 12/13/2010: 3948; 12/15/2010: 3987; 12/21/2010: 4033; 12/22/2010: 4033; 1/3/2011: 4390; 1/4/2011: 4396; 1/5/2011: 4536; 1/6/2011: 4694; 1/7/2011: 4780; 1/11/2011: 4807; 1/13/2011: 4884; 1/14/2011: 4925; 1/19/2011: 5231; 1/20/2011: 5258; 1/21/2011: 5414; 1/24/2011: 5595; 1/27/2011: 5644; 2/4/2011: 5728; 2/7/2011: 5799; 2/11/2011: 5942; 2/14/2011: 6195; 2/17/2011: 6340; 2/20/2011: 6436; 2/21/2011: 6486; 2/23/2011: 6506; 2/24/2011: 6521; 3/1/2011: 6650; 3/3/2011: 6714; 3/4/2011: 6743; 3/8/2011: 6772; 3/9/2011: 6869; 3/11/2011: 7011; 3/16/2011: 7135; 3/18/2011: 7204; 3/21/2011: 7237; 3/22/2011: 7242; 3/24/2011: 7242; 3/25/2011: 7296; 3/27/2011: 7352; 3/28/2011: 7381; 3/29/2011: 7436; 3/31/2011: 7597; 4/1/2011: 7657; 4/3/2011: 7795; 4/4/2011: 7836; 4/5/2011: 7939; 4/7/2011: 7944; 4/8/2011: 7944; 4/10/2011: 8036; 4/11/2011: 8120; 4/13/2011: 8123; 4/15/2011: 8223; 4/17/2011: 8341; 4/18/2011: 8356; 4/19/2011: 8372; 4/20/2011: 8397; 4/22/2011: 8521; 4/24/2011: 8562; 4/25/2011: 8563; 4/26/2011: 8578; 4/27/2011: 8630; 4/28/2011: 8702; 4/29/2011: 8726; 5/1/2011: 8842; 5/2/2011: 8845; 5/3/2011: 8865; 5/4/2011: 8871; 5/5/2011: 8881; 5/8/2011: 8938; 5/9/2011: 8962; 5/10/2011: 9004; 5/11/2011: 9041; 5/12/2011: 9050; 5/16/2011: 9051; 5/18/2011: 9056; 5/20/2011: 9071; 5/23/2011: 9188; 5/25/2011: 9212; 5/27/2011: 9225; 5/31/2011: 9355; 6/6/2011: 9377; 6/8/2011: 9432; 6/14/2011: 9454;
Activity
Status
Award of Subcontract
Preparation for Installation
Component delivery: June 2009 to 3/23/10
Foundation installed: December 18, 2009
Documentation delivery: December 2009 to 1/29/10
Turbine Installation
January 26, 2010
Turbine Commissioning
Ventera Commissioning: January 28, 2010
Inverter Commissioning: March 23, 2010
Turbine O&M and Testing
Safety and Function Test
Under Peer Review
Power Performance Test
Under Peer Review (restarted on July 27, 2010)
Hrs of valid data (60 required)
548
Bins completed (3.5-14 m/s required)
0.5-25.0 m/s
Acoustic Noise Test
Data Under Analysis
Power Quality Test
Not Applicable
Duration Test
Data Collection Complete (restarted on July 14, 2010)
Months of operation (6 required)
9.5 (158%)
Hours of power production (2,500 required)
2,915 (117%)
Hours of power production in winds greater than 10.2 m/s (250 required)
777 (311%)
Hours of power production in winds greater than 15.3 m/s (25 required)
259 (1,038%)
kWh of production, cumulative
8,726
Turbine Removed
Not applicable
Post-test Inspection
Not started
Final Documentation
Not started
Project Review Meeting
Not started