Entegrity Wind Systems
Entegrity Wind Systems' EW50 wind turbine. Text Version
As part of the National Renewable Energy Laboratory and U.S. Department of Energy (NREL/DOE) Independent Testing project, NREL is testing Entegrity Wind Systems' EW50 turbine at the National Wind Technology Center (NWTC). The EW50 is a 50-kW, three-bladed, horizontal-axis downwind small wind turbine. The turbine's rotor diameter is 15 meters, and its hub height is 30.5 meters. It has a three-phase induction generator that operates at 480 volts AC.
Testing Progress
The date of the information in this progress report is May 1, 2011. Supporting data and explanations for data provided in this table will be provided in the final reports once testing is complete. Data presented are preliminary and subject to revision.
Cumulative Energy Production
| Activity | Status |
|---|---|
| Award of Subcontract | August 19, 2008 |
| Preparation for Installation | Foundation installed: May 12, 2008 Components received: 2/4/09 to 3/9/09 Documentation received: February 27, 2009 |
| Turbine Installation | March 2, 2009 |
| Turbine Commissioning | Entegrity Commissioning: March 6-27, 2009; Readiness Verification: March 11, 2009; Data Acquisition System check: April 2, 2009 |
| Turbine O&M and Testing | |
| Safety and Function Test | Under Peer Review |
| Power Performance Test | Wind Turbine Generator System Power Performance Test Report for the Entegrity EW50 Wind Turbine |
Hrs of valid data (60 required) |
968 |
Bins completed (3.5-14 m/s required) |
0.5-22 m/s |
| Acoustic Noise Test | Writing Report |
| Power Quality Test | Discontinued |
| Duration Test | Writing Report |
Months of operation (6 required) |
20 (333%) excluding Sept. 2010 |
Hours of power production (2,500 required) |
2,606 (104%) |
Hours of power production in winds greater than 10.2 m/s (250 required) |
581 (233%) |
Hours of power production in winds greater than 15.3 m/s (25 required) |
135 (539%) |
kWh of production, cumulative |
45,632 |
| Turbine Removed | Not applicable |
| Post-test Inspection | Not started |
| Final Documentation | Not started |
| Project Review Meeting | Not started |