Abundant Renewable Energy's ARE 442 Wind Turbine Testing and Results

A video of Abundant Renewable Energy's ARE 442 wind turbine. Text Version

As part of the National Renewable Energy Laboratory and U.S. Department of Energy (NREL/DOE) Independent Testing project, NREL tested Abundant Renewable Energy's ARE 442 turbine at the National Wind Technology Center (NWTC). The ARE 442 is a 10-kilowatt (kW), three-bladed, horizontal-axis upwind small wind turbine. It has a hub height of 30.9 meters and a rotor diameter of 7.2 meters. The turbine has a single-phase permanent-magnet generator that operates at variable voltages up to 410 volts AC.

Testing Summary

The summary of the tests is below with the final reports.

Graph showing the kilowatt hours by date for the Abundant Renewable Energy turbine.  It starts at June 8, 2008 at 0 kilowatt-hours and gradually rises to 12,215 by December 10, 2009.
Activity Status
Award of Subcontract January 3, 2008
Preparation for Installation Foundation poured: April 30, 2008
Last Components received: March 4, 2008
Documentation received: March 3, 2008
Turbine Installation June 6-11 2008
Turbine Commissioning June 12, 2008
Turbine O&M and Testing  
Safety and Function Test Wind Turbine Safety and Function Test Report for the ARE 442 Wind Turbine
Power Performance Test Wind Turbine Generator System Power Performance Test Report for the ARE442 Wind Turbine
Hrs of valid data (60 required)
303.7
Bins completed (3-14 m/s required)
0.5-18 m/s
Acoustic Noise Test Wind Turbine Generator System Acoustic Noise Test Report for the ARE 442 Wind Turbine
Power Quality Test Not applicable
Duration Test Wind Turbine Generator System Duration Test Report for the ARE 442 Wind Turbine
Months of operation (6 required)
9.5
Hours of power production (2,500 required)
3240 (130%)
Hours of power production in winds greater than 10.2 m/s (250 required)
553 (221%)
Hours of power production in winds greater than 15.3 m/s (25 required)
157 (628%)
kWh of production, cumulative
12,215
Turbine Removed December 14, 2009
Post-test Inspection Completed
Final Documentation Completed
Project Review Meeting Completed