Abundant Renewable Energy
A video of Abundant Renewable Energy's ARE 442 wind turbine.
Text Version
As part of the National Renewable Energy Laboratory and U.S. Department of Energy (NREL/DOE) Independent Testing project, NREL is testing Abundant Renewable Energy's ARE 442 turbine at the National Wind Technology Center (NWTC). The ARE 442 is a 10-kW, three-bladed, horizontal-axis upwind small wind turbine. It has a hub height of 30.9 meters and a rotor diameter of 7.2 meters. The turbine has a single-phase permanent-magnet generator that operates at variable voltages up to 410 volts AC.
Testing Progress
The date of the information in this progress report is November 3, 2009. Supporting data and explanations for data provided in this table will be provided in the final reports once testing is complete. Data presented are preliminary and subject to revision.
Cumulative Energy Production
| Activity | Status |
|---|---|
| Award of Subcontract | January 3, 2008 |
| Preparation for Installation | Foundation poured: April 30, 2008 Last Components received: March 4, 2008 Documentation received: March 3, 2008 |
| Turbine Installation | June 6-11 2008 |
| Turbine Commissioning | June 12, 2008 |
| Turbine O&M and Testing | |
| Safety and Function | Report under review |
| Power Performance | Report under review |
Hrs of valid data (60 required) |
303.7 |
Bins completed (3-14 m/s required) |
0.5-18 m/s |
| Acoustic Noise | Data collection complete; analysis underway |
| Power Quality | Not applicable |
| Duration Test | Report under review |
Months of operation (6 required) |
9.5 |
Hours of power production (2,500 required) |
3240 (130%) |
Hours of power production in winds above 10.2 m/s (250 required) |
553 (221%) |
Hours of power production in winds above 15.3 m/s (25 required) |
157 (628%) |
KWH of production, cumulative |
11,350 |
| Post-test Inspection | Not started |
| Final Documentation | Not started |
| Project Review Meeting | Not started |






