1BMSGlobal TSP-70009/29/202309:39:0009/29/202313:48:00Due to an NREL-wide power outage caused by Xcel Energy, the following BMS instruments were down due to no power: 501A-UVA, TSP-700, UVSAT, UVSBT, SolarSIM-D2, CUVA2, All WISERs, CUVB2, UVB-1, 501A-UVB, MS210W, SPN1, TSI-880, PGS-100, POM-01, TWC, ASI-16.
2BMSGlobal TSP-70008/06/202307:12:0008/06/202312:06:00Due to an electrical systems failure at NREL, the following BMS instruments were down due to no power: 501A-UVA, TSP-700, UVSAT, UVSBT, SolarSIM-D2, CUVA2, All WISERs, CUVB2, UVB-1, 501A-UVB, MS210W, SPN1, TSI-880, PGS-100, POM-01, TWC, ASI-16.
3BMSGlobal TSP-70011/17/202007:21:0011/17/202007:45:00Due to a scheduled NREL/SRRL power outage, to replace a surge protection device on the SRRL building, the following BMS instruments were down: 501A-UVA, TSP-700, UVSAT, UVSBT, SolarSIM-D2, CUVA2, WISERs (Horiz;2-Axis;1-Axis), CUVB2, UVB-1, 501A-UVB, MS210W, SPN1, TSI-880, PGS-100, POM-01, TWC, ASI-16.
4BMSGlobal TSP-70005/18/202013:03:0012/15/202119:31:00DATA CORRECTED on 12/17/2021: Irradiances were increased by 0.675% due to revised BORCAL report for all BMS shortwave radiometers calibrated in 2020 and 2021.
5BMSGlobal TSP-70003/09/201908:40:0003/09/201912:59:00Due to a scheduled NREL/SRRL power outage, to install power meters on the SRRL building, the following BMS instruments were down: 501A-UVA, TSP-700, UVSAT, UVSBT, SolarSIM-D2, CUVA2, WISERs, CUVB2, UVB-1, 501A-UVB, MS210W, SPN1, TSI-880, PGS-100, POM-01, TWC, ASI-16.
6BMSGlobal TSP-70004/01/201800:00:0004/14/201823:59:00The TSP-700 was reading low (up to about 100 W/m^2 at noon), problem was unknown and went away on its own.
7BMSGlobal TSP-70004/25/201507:20:0004/25/201509:39:00Due to a scheduled NREL/SRRL power outage, to remove wiring from the building ATS, the following BMS instruments were down: TSP-700, UVSAT, UVSBT, CUVA1, CUVA2, CUVB1, CUVB2, UVB-1, 501A, MS210W, SPN1, TSI-880, PGS-100, POM-01, TWC, EFM-100, MS-7XX, LI-1800.
8BMSGlobal TSP-70005/29/201400:00:0006/09/201411:57:00The TSP-700 was reading low. Four screws behind the patch panel for this signal were retightened which fixed the problem.
9BMSGlobal TSP-70012/28/201306:46:0012/28/201315:59:00Due to a scheduled NREL power outage, to upgrade campus electrical infrastructure, the following BMS instruments were down: TSP-1, TSP-700, UVSAT, UVSBT, CUVA1, CUVA2, CUVB1, CUVB2, UVB-1, 501A, MS210W, SPN1, TSI-880, PGS-100, POM-01, TWC, EFM-100.
10BMSGlobal TSP-70012/21/201307:00:0012/21/201316:22:00Due to a scheduled NREL power outage, to upgrade campus electrical infrastructure, the following BMS instruments were down: TSP-1, TSP-700, UVSAT, UVSBT, CUVA1, CUVA2, CUVB1, CUVB2, UVB-1, 501A, MS210W, SPN1, TSI-880, PGS-100, POM-01, TWC, EFM-100.
11BMSGlobal TSP-70003/02/201308:06:0003/02/201318:24:00Due to a scheduled NREL power outage, to upgrade campus power capacity, the following BMS instruments were down: TSP-1, TSP-700, UVSAT, UVSBT, CUVA1, CUVA2, CUVB1, CUVB2, UVB-1, 501A, MS210W, SPN1, TSI-880, PGS-100, POM-01, TWC, EFM-100.
12BMSGlobal TSP-70005/26/201206:15:0005/26/201207:12:00Due to a planned power outage for SRRL electrical work, the following BMS instruments were down: TSP-1, TSP-700, UVSAT, UVSBT, CUVA1, CUVA2, CUVB1, CUVB2, UVB-1, 501A, MS210W, SPN1, PGS-100, POM-01, TWC.
13BMSGlobal TSP-70011/12/201111:59:0011/12/201113:26:00Due to an undervoltage followed by a power outage at 13:12, the following BMS instruments may be reading bogus or invalid data: TSP-1, TSP-700, UVSAT, UVSBT, CUVA1, CUVA2, CUVB1, CUVB2, UVB-1, 501A, MS210W, SPN1, TWC.
14BMSGlobal TSP-70009/08/201105:56:0009/08/201109:19:00Due to a planned power outage for SRRL construction activities, the following BMS instruments were down: TSP-1, TSP-700, UVSAT, UVSBT, CUVA1, CUVA2, CUVB1, CUVB2, UVB-1, 501A, MS210W, SPN1, PGS-100, POM-01, TWC.
15BMSGlobal TSP-70006/14/201113:01:0006/14/201113:14:00Due to a planned power outage for SRRL construction activities, the following BMS instruments were down: TSP-1, TSP-700, UVSAT, UVSBT, CUVA1, CUVA2, CUVB1, CUVB2, UVB-1, 501A, MS210W, SPN1, TSI-880, PGS-100, POM-01, EFM-100.
16BMSGlobal TSP-70005/25/201105:19:0005/26/201112:16:00Due to a planned power outage for SRRL construction activities, the following BMS instruments were down: TSP-1, TSP-700, UVSAT, UVSBT, CUVA1, CUVA2, CUVB1, CUVB2, UVB-1, 501A, MS210W, SPN1, TSI-880, PGS-100, POM-01, EFM-100.
17BMSGlobal TSP-70005/17/201114:20:0005/17/201114:48:00Due to a planned power outage for SRRL construction activities, the following BMS instruments were down: TSP-1, TSP-700, UVSAT, UVSBT, CUVA1, CUVA2, CUVB1, CUVB2, UVB-1, 501A, MS210W, SPN1, TSI-880, PGS-100, POM-01, EFM-100.
18BMSGlobal TSP-70005/07/201105:18:0005/07/201111:45:00Due to a planned power outage for SRRL construction activities, the following BMS instruments were down: TSP-1, TSP-700, UVSAT, UVSBT, CUVA1, CUVA2, CUVB1, CUVB2, UVB-1, 501A, MS210W, SPN1, TSI-880, PGS-100, POM-01, EFM-100.
19BMS0212-2Global TSP-70004/17/201112:00:00There is an occasional drastic noise or signal drop out problem with the SRRL BMS TSP-700 during this time. The instrument connections will be re-seated the next time a problem occurs.
20BMSGlobal TSP-70004/15/201106:11:0004/15/201106:50:00Due to a planned power outage for SRRL construction activities, the following BMS instruments were down: TSP-1, TSP-700, UVSAT, UVSBT, CUVA1, CUVA2, CUVB1, CUVB2, UVB-1, 501A, MS210W, SPN1, TSI-880, PGS-100, POM-01, EFM-100.
21BMS0212-2Global TSP-70010/04/201013:00:0010/06/201008:00:00There is an occasional drastic noise or signal drop out problem with the SRRL BMS TSP-700 during this time. The connector at the J-box was re-seated.
22BMS0212-2Global TSP-70009/22/201012:00:0010/04/201008:00:00There is an occasional drastic noise or signal drop out problem with the SRRL BMS TSP-700 during this time. All screws in TSP-700 power supply box were retightened.
23BMS0212-2Global TSP-70008/11/201000:00:0008/29/201019:00:00There is an occasional drastic noise or signal drop out problem with the SRRL BMS TSP-700 during this time. Problem appears to have stopped on 8/29/2010.
24BMS0212-2Global TSP-70012/13/200900:00:0012/17/200915:30:00There is an occasional drastic noise or signal drop out problem with the SRRL BMS TSP-700 during this time. Some days there is no problem. (4) screws in the patch panel for this channel were retightened which seemed to fix the problem.
25BMS0212-2Global TSP-70012/09/200910:52:0012/09/200914:22:00Due to a power outage (and bad power) at NREL, the following BMS instruments were down: TSP-1, TSP-700, UVSAT, UVSBT, CUVA1, CUVA2, CUVB1, CUVB2, UVB-1, 501A, MS210, SPN1, Snow Depth, TSI-880, POM-01.