| Project Overview |
| Project Name: |
Guzmán |
| Country: |
Spain |
| Location: |
Palma del Río (Córdoba) |
| Owner(s): |
FCC Energy
(70%)
Mitsui
(30%)
|
| Technology: |
Parabolic trough |
| Turbine Capacity: |
Net: 50.0 MW
Gross: 50.0 MW |
| Status: |
Operational |
| Start Year: |
2012
|
Do you have more information, corrections, or comments?
Guzmán
This page provides information on Guzmán, a concentrating solar power (CSP) project, with data organized by background, participants, and power plant configuration.
| Status Date: |
March 18, 2013
|
Background
| Technology: |
Parabolic trough |
| Status: |
Operational |
| Country: |
Spain |
| City: |
Palma del Río |
| Region: |
Córdoba |
| Lat/Long Location: |
37°9′
7.0″
North,
5°16′
16.0″
West |
| Land Area: |
200 hectares |
| Electricity Generation: |
104,000 MWh/yr
(Estimated)
|
| Contact(s): |
David García |
| Company: |
FCC Energy |
| Break Ground: |
July 2010 |
| Start Production: |
July 2012 |
| PPA/Tariff Type: |
Real Decreto 661/2007 |
| PPA/Tariff Rate: |
27.0 Euro cents per kWh |
| PPA/Tariff Period: |
25 years
|
| PPA/Tariff Information: |
Feed-in Tariff |
| Project Type: |
Commercial |
Participants
| Developer(s): |
FCC Energy |
| Owner(s) (%): |
FCC Energy
(70%)
Mitsui
(30%)
|
| EPC Contractor: |
FCC, Abantia, SerIDOM (IDOM Group) |
Plant Configuration
Solar Field
| Solar-Field Aperture Area: |
310,406 m² |
| # of Solar Collector Assemblies (SCAs): |
384 |
| # of Loops: |
96 |
| # of SCAs per Loop: |
4 |
| SCA Aperture Area: |
817 m² |
| SCA Length: |
150 m |
| # of Modules per SCA: |
12 |
| SCA Manufacturer (Model): |
Sener
(SenerTrough)
|
| Mirror Manufacturer (Model): |
Flabeg (RP3)
|
| # of Heat Collector Elements (HCEs): |
13,824 |
|
HCE Manufacturer (Model): |
Schott (PTR-70) |
| Heat-Transfer Fluid Type: |
Dowtherm A |
| Solar-Field Inlet Temp: |
293°C |
| Solar-Field Outlet Temp: |
393°C |
| Solar-Field Temp Difference: |
100°C |
Power Block
| Turbine Capacity (Gross): |
50.0 MW
|
| Turbine Capacity (Net): |
50.0 MW |
| Turbine Manufacturer: |
Man-Turbo |
| Turbine Description: |
5 extractions |
| Output Type: |
Steam Rankine |
| Power Cycle Pressure: |
100.0 bar |
| Cooling Method: |
Wet cooling |
| Cooling Method Description: |
Cooling Towers |
| Fossil Backup Type: |
HTF Heaters (3x15MWt) |
| Backup Percentage: |
12%
|
Thermal Storage