BrightSource PG&E 5
This page provides information on BrightSource PG&E 5, a concentrating solar power (CSP) project, with data organized by background, participants, and power plant configuration.
| Status Date: |
January 21, 2011
|
Background
| Technology: |
Power tower |
| Status: |
Under development |
| Country: |
United States |
| City: |
TBD |
| State: |
California |
| Electricity Generation: |
573,000 MWh/yr
(Expected/Planned)
|
| Contact(s): |
BrightSource Energy |
| Key References: |
Web site
|
| Break Ground: |
2012 |
| Start Production: |
July 2016 |
| PPA/Tariff Date: |
September 24,
2009 |
| PPA/Tariff Period: |
25 years
|
Participants
| Developer(s): |
BrightSource Energy |
| Generation Offtaker(s): |
Pacific Gas & Electric (PG&E) |
Plant Configuration
Solar Field
Power Block
| Turbine Capacity (Gross): |
200.0 MW
|
| Output Type: |
Steam Rankine |